Construction crews continue to work tirelessly on all aspects of building our new school. We are pleased with the progress at this point.

On the top floor, the floors are complete, lockers are installed, cabinets are in, & doors and windows are installed, everything is painted. The second floor is coming along with the same progress with coat racks to be installed yet. Current projects include popping in the individual ceiling tiles, finishing ceramic corridor on the first floor, and installing the gym floor. The playground will be sodded shortly and the turf field is almost excavated.

Our school is going to be spectacular and it takes time when crews are doing a quality job.

We will keep you posted with more progress updates.

Continue to enjoy your summer!